Thursday, March 15, 2018

News Update

Following the initial commissioning of Western Link on 7 December 2017, enabling the transfer of up to 900 MW across the link, commissioning has progressed to the extent that the link is now operating at up to 1125 MW. Work is continuing at Hunterston to enable the link to operate at its full capacity of 2250 MW. This is expected to be in June 2018. 